|

Volume 14: Number 4: October 2007
CONTAINERS AND CARGOES
Stow collapse raises the possibility of a new industry code of best practice
The collapse of a relatively small stack of containers
onboard the MV ANNABELLA lead investigating
officials to identify serious deficiencies in both the
shoreside and ship stowage planning procedures.
When combined with concerns about
previous incidents of stow collapse, this
resulted in the UK authorities suggesting
that the time is right for the construction of
a new code of best practice for stowage
planning of container vessels.
The detailed report drawn up by the UK
Marine Accident Investigation Branch
(MAIB) into the ANNABELLA incident
identifies faults with stowage planning
procedures that are familiar to the
Association. The MAIB has hinted that their
on-going investigation into the MSC
NAPOLI incident is also likely to reveal
deficiencies in this area which may need
to be addressed by the industry. The MAIB
report also provides ships officers and
stowage planners with a useful reminder
of the many factors which can give rise to
the collapse of a stow.
The ANNABELLA was transiting the Baltic
Sea when, on the morning of 26 February,
the crew discovered a collapse of 7 x 30
containers in bay 12 of #3 hold. During the previous night the Master had altered
course and reduced speed in order to reduce
the effect of heavy weather (Beaufort force
7/8). The stack had collapsed into the forward
part of the hold; the lower containers being
partially crushed, the upper containers
not suffering significant damage. Rather
worryingly these upper containers were tank
containers fully loaded with butylene gas
(IMDG Class 2.1). Later that day, on arrival at
Helsinki, the Harbour Master decided that
because of the proximity of populated areas
to the port, it would be unsafe for the vessel
to berth and attempt to discharge the
damaged hazardous cargo containers at
Helsinki. The vessel was ordered to Kotka. At
Kotka a 400 metre restriction zone was
established around the vessel when it
berthed at the container terminal and salvage
experts were engaged to advise on a discharge
plan. After ascertaining that there was no
hazardous gas leaking into #3 cargo hold, the
containers were successfully discharged. Apart
from the inconvenience and costs of being
diverted to Kotka, the consequences of the
collapse of stow were relatively minimal
compared to many of the incidents of
collapsed stows with which the Association
has dealt. Indeed, the potentially disastrous
consequences had the cargo of butylene
leaked and then ignited can be imagined.
Despite the minimal consequences, the MAIB
investigated the circumstances of the collapse
in a comprehensive and detailed manner.
The stack of 7 x 30 containers in the centre of
bay 12, hold #3 were loaded at the ECT
terminal in Rotterdam, below deck. As 30
containers are considered irregular, the
lashing and securing manual provided that
lashing bars should be applied to their
forward end. Unfortunately, no such lashing
bars were applied. Further, the total weight of
the seven containers was found to be 225
tonnes, whereas the cargo securing manual
indicated the maximum permissible stack
weight for 30 containers loaded in this
location was 150 tonnes. Furthermore the
lower four containers in the stack only had a
maximum allowable stack weight of 100
tonnes i.e. were not built to ISO Standards.
As is often the case, stowage planning was
undertaken ashore; on this occasion by
charterers stowage planners. Importantly,
although the planners were aware of
ANNABELLAs stowage capabilities and also
held some details of her stability, they
ultimately relied on the ships staff to alert
them to any errors in the stowage plan and
expected the Chief Officer to check every
aspect of the stowage plan before the vessel
began loading. The shoreside planners were
aware of previous incidents involving ships of
the same class, where their plans to load 30
containers exceeded the allowable stack
weights. In these cases the planners had been
alerted to the problem by the ships staff, and
suitably amended plans agreed. Despite this,
the planners failed to review their planning
procedures for this type of vessel when
loading these 30 containers and continued to
rely on the ships Chief Officer to check the
stowage plan. In any event the shoreside
stowage planners software seems to have
had difficulty dealing with the in-put of 30
containers and defaulted to 40 containers
when analysing the maximum permissible
stack weight. This resulted in an incorrect
maximum allowable stack weight of 240
tonnes in hold #3. Accordingly the subject
stack, at 225 tonnes, triggered no alarms. The
MAIB noted that the software used by the
charterers for planning purposes was not the
same as that onboard the vessel and that
there is no requirement for the planners
programme to be checked or approved by
an external authority.
The vessel received the proposed stowage
plan by email at 1200 hrs on 22 February,
some 6 hours before berthing and
commencement of loading operations. The
Chief Officer checked that the stow plan was
acceptable in terms of bending and sheer
stresses, hazardous cargo distribution and the
requirements of the vessels cargo securing
manual. However the software onboard the
ship only checked cargo securing
arrangements for containers stowed above
deck. Further, although the software had an
alarm function designed to operate if
individual stack weights were exceeded, the
software had not been correctly programmed
to recognise 30 containers and did not alarm
when the weight of the stack of 7 x 30
containers was in-put.
The ships software (lashing and securing
module) had not been approved by a
Classification Society. The ships cargo securing
manual had been approved and did contain
lashing arrangements and specific stack
weights for 30 containers. Details of these
lashing arrangements for 30 containers were
located in an annex to the manual but the
annex was not referred to in a list of reference
documents in the introduction of the cargo
securing manual. The implication being
that it was not easy to locate. The general
lashing plan shown in the manual was also
permanently displayed on the cargo office
wall and clearly indicated that the maximum
stack weight on the tank top was 150 tonnes
and not 240 tonnes. (Based on a maximum
GM of 0.8m).This plan was not referred to by
the Chief Officer. Unfortunately, the lowest
4 of the 30 containers in the collapsed stack
were themselves not capable of supporting a
stack weight of 150 tonnes. According to their
CSC rating they were limited to a stack weight
of 100.5 tonnes.
It appears therefore that the stack not only
failed to comply with the correct 30 container
150 tonnes limit as per the approved lashing
and securing manual but that this limit was in
fact not appropriate because the vessels GM
was actually 1.8m. The stow was additionally
flawed because the stack limit was based on
ISO standard containers and ISO Standard
containers were not loaded.
The failings of the Chief Officer are perhaps
obvious in that he failed to refer to the
detailed annexes of the cargo securing
manual to establish proper stowage of the 30
containers. He also seemed oblivious to the
effect of GM on lashing and securing
arrangements, i.e. as a factor affecting the
applicability of the cargo securing manual
itself. However the MAIB have thoughtfully
gone beyond the omissions of the Chief
Officer and identified the failings of the
operations and processes involved.
Among the prime factors relating to the
casualty was the insufficient spare time
allowed for the Chief Officer to become fully
conversant with the full details of the vessels
cargo securing manual and its many annexes
before he took over as Chief Officer. Further,
the integrated container and lashing module
of the ships software was not Class approved;
the approval process would no doubt have
identified and eliminated the programming
error which converted 30 container to 40. The
fact that the lashing and securing manual was
only applicable to a GM of 0.8 meant that the
Chief Officer did not have available to him the
requisite reductions in allowable stack weights
and enhanced securing requirements when
sailing with a GM greater than 0.8m. (For
operational reasons, this vessel was required
regularly to sail with GM in excess of 0.8m).
The MAIB report went on to identify
deficiencies in the shoreside procedures.
Namely, that the charterers loading computer
system had not been independently
examined and that this contributed to the
programming errors not being detected.
Further, that the cargo planners had no access
to detailed information of the ANNABELLAs
cargo securing manual and accordingly the
operational restrictions contained in these
documents were not taken into account
during the planning process. These
deficiencies have to be considered in the
context of the speed of operations which
meant that the Chief Officer is unlikely to have
the necessary influence to stop or slow the
operation while he makes a detailed check of
all aspects of the stow plan or individual
containers. Without such a check it is
inevitable that errors made during the
planning loading process will be undetected.
It is perhaps this latter issue which needs to
be emphasised. If the Chief Officer does not
have the time nor influence to affect the
stow then the deficiencies of the shoreside
stowage planning process become critical.
One causative factor over which neither the
Chief Officer nor the shoreside stowage
planners could have exercised their influence
was the lack of a method of identifying
containers which are non-ISO standard.
In addition to the recommendations to the
ship managers and charterers of the vessel,
the MAIB are so concerned at what appears to
be a pattern of incidents involving the loss of
containers overboard that they have seen fit
to recommend to the International Chamber
of Shipping that the industry develops,
promotes and adheres to a best practice
safety code. This would ensure ships staff had
the resources and opportunity to safely
oversee the loading and securing of cargo
and that either cargo securing manuals are in
a format which provides ready and easy
access to all relevant cargo loading and
securing information or, loading computer
programmes - both shipboard and shoreside
- incorporate the full requirements of a
vessels cargo securing manual and are
properly approved so that officers can place
full reliance on the information provided. The
MAIB went on to suggest that the availability
or otherwise of a reliable, approved, loading
computer programme should be a factor in
determining appropriate levels of manning for
vessels on intensive schedules.
The Association has little experience of the
specific difficulties relating to 30 containers
illustrated in the above report but does have
considerable experience of the fundamental
deficiencies in stowage planning procedures
which feature regularly in claims presented to
the Association. Such claims tend to manifest
themselves, not in the exceeding of stack
weights, but rather in the inappropriate
distribution of heavy containers within a
particular stack, the result however is the
same: collapse of stow. The reports emphasis
on the failure or inability to take in account
GMs higher than that provided in lashing and
securing manuals is also a familiar factor in
the incidents reported to the Association.
Styrene monomer
To those that specialise in the trade, it has been known
for many years that great care should be taken if a ship that has previously
carried a cargo of styrene monomer is offered for the carriage of sensitive
cargoes such as edible oils/fats, methanol or other high purity chemical cargoes.
Styrene monomer
is a colourless, oily
liquid with a strong
odour. Used in the
manufacture of
polystyrene,
polyesters and
various types of resin, it is one of the most
frequently shipped chemical cargoes.
Styrene monomer is difficult to clean from
tankers as it is prone to absorption into
organically coated cargo tanks, particularly
tanks coated with epoxy paint, from which it
then desorbs naturally over time. For this
reason, FOSFA (Federation of Oils, Seeds and
Fats Associations) has banned the carriage of
edible oils and fats intended for human and
animal consumption in tanks where styrene
monomer is amongst the last 3 cargoes
carried. Many manufacturers of methanol also
insist that their cargoes should not be carried
in vessels that have carried styrene monomer
previously. However, the growth of the
methanol trade in recent years, particularly its
rapid expansion in the Chinese market, which
looks set to continue, has inevitably meant
that a wider range of ship owners and
charterers have become involved in the
carriage of methanol. Not all such new
entrants to the market have experience of the
risks involved in carrying methanol or other
high purity chemical cargoes where styrene
monomer has been carried as a previous
cargo. For this reason, we wish to bring to
Members attention a recent case in which the
Club was involved which illustrates the
potential problems.
The case involved the carriage of chemical
grade methanol from Indonesia to China. The
ships centre tanks were made from or clad
with stainless steel, while the wing tanks were
coated with an epoxy-type paint. Amongst its
previous two cargoes the ship had carried
styrene monomer in both the stainless steel
and epoxy coated tanks.
Prior to loading the methanol, the tanks were
cleaned to the standard customarily required
after carrying a cargo of styrene monomer.
The cleaning method used was capable of
removing all significant residues of the
styrene monomer from the tank surfaces,
pumps and lines. The ship was accepted by
the load port surveyor and also passed a
subsequent wall-wash survey and first-foot
analysis. No residual odour of styrene
monomer was noted at the load port.
Upon arrival at the discharge port, the
methanol in the wing tanks (i.e. those coated
with epoxy paint) was found to be
contaminated. The methanol carried in the
stainless steel centre tanks was, however,
within specification.
An expert was appointed by the Club and
concluded that styrene monomer present in
the paint coatings of the wing tanks had
desorbed during the voyage, contaminating
the methanol. The experts view was that the
tank cleaning appeared to have been carried
out to the highest industry standards for
cleaning styrene monomer but this was
insufficient to prevent it from subsequently
desorbing. Furthermore, styrene monomer
residues in the tank coatings had not been
detected by routine analyses carried out at
the load port prior to the full cargo being
loaded nor by smell.
In the experts view, the only way to remove
styrene monomer that has been absorbed
into tank paint coatings is to allow it to
desorb naturally over a period of time.
This could take months or even years. In this
case the level of cargo contamination in the
tanks where styrene monomer had been the
last cargo was markedly greater than in the
tanks where it had been the second last
cargo, indicating natural desorption over time.
Increasing the temperature of the tank
surfaces, for example by loading hot liquid,
will accelerate the rate of desorption and this
may, therefore, reduce the time taken to
achieve thorough cleaning.
In order to avoid claims, Members should
avoid loading cargoes of methanol or other
high purity chemical cargoes in tanks with
epoxy paint coatings which have previously
held styrene monomer unless they have
expert confirmation that there is no longer a
risk that the styrene monomer will desorb.
Zinc-rich tank coatings also do not absorb
styrene monomer residues but they are
porous and can, therefore, to a certain degree,
retain elements of previous cargoes. Although
this problem is not insurmountable, it does
make zinc-rich coatings more difficult to clean
than stainless steel tanks. Ideally such sensitive
cargoes should only be loaded in stainless
steel tanks, which are easily cleaned and do
not absorb styrene monomer.
REGULATORY UPDATE
Black sea: Grey water
Many owners are no doubt aware of the
enthusiasm with which the authorities in the Black Sea levy fines and penalties
on ships in their waters. We have recently been involved in a matter, which
although not generating a significant fine, did have an unintended consequence.
In August this year, a container ship operated
by one of the Associations liner Members,
called at Ilyichevsk. Upon arrival, it was alleged
that the ship had allowed grey water to be
discharged overboard and the local authorities
notified their intention to investigate.
Following an onboard investigation, it was
alleged that two valves on the vessels sewage
system had not been closed properly and as a
result, had led to an overboard discharge. This
was considered to be a violation of MARPOL
as well as a violation of local regulations and
the authorities signalled their intention to levy
a fine on the ship. The fine was assessed to be
in the region of USD3,000 - USD3,500.
With the intervention of the Associations local
correspondent, it was established that the
valves in question served the ships refrigeration
and air conditioning systems and not the
sewage system and that grey water from the
ships sewage system was pumped directly
into a sewage tank. This was communicated
to the authorities and a further attendance on
board was convened with the local authorities.
Although the local authorities were
subsequently able to agree with the findings
of the surveyor appointed by the Member
unfortunately they were unable to locate the
sewage tank on board, in spite of detailed
ships plans. Under the circumstances, this was
considered to be a violation of Ukrainian
environmental legislation and it was decided
to levy a fine on the ship!
In view of time constraints and that a
continued discussion over the validity of the
fine would have led to further delays to the
ship, the decision was taken to settle the fine
rather than incur additional costs.
It would seem that there is little that can be
done to stop the local authorities from
pursuing these matters with excessive
enthusiasm. Members are reminded however
to ensure that the local correspondent is
contacted as a matter of urgency as soon as
there is any indication from local authorities
that attempts are being made to pursue an
environmental fine against a ship for alleged
discrepancies in MARPOL or local regulations.
New SOLAS regulation dictates the phased introduction of
long range identification and tracking (LRIT)
A new regulation that is likely to enter into
force on 1 January 2008 will introduce the
requirement for the long range identification
and tracking of ships (LRIT). Although there is
a phased implementation programme ship
owners will need to familiarise themselves
with the new technical requirements and satisfy themselves that the GMDSS equipment
on board their ships has the required
capabilities as dictated by the new regulation.
The UK Maritime and Coastguard Agency will
shortly be issuing a Marine Information Note.
NAVIGATION AND SEAMANSHIP
How good is the data on which your charts are based?
Most mariners
are aware that there is great variation in the extent to which waters around the
world have been surveyed.
Navigation Charts indicate the hydrographic
surveys which relate to the charted area. A
recent incident in UK waters has highlighted
that it is not only the more remote coastal
waters that have not been surveyed or
charted by modern methods. Many of the
developed littoral nations need to identify
areas of their coast which have historically
been ignored for the purpose of
hydrographic survey as they might require
attention by virtue of increased utilisation by
various sectors of maritime industry.
The jack-up barge OCTOPUS was being
towed from Kirkwall to Seal Skerry Bay in the
Orkney Islands by the tug HARALD. The
voyage was planned by the HARALDs skipper
using Admiralty paper charts. The echo
sounder was running throughout the voyage
although turbulence caused by the fast
flowing tides resulted in the trace becoming
illegible. Once clear of the approaches to
Kirkwall the tugs skipper lowered the barge
legs from 5 metres to 9 metres in order to
improve the OCTOPUSs stability during
anticipated swell when passing east of
Shapinsay. The possibility existed of
proceeding to the east of the Green Holm
Islands but on approach the strong spring
ebb tide appeared to set the tug and tow to
the west which would set them towards
Green Holm Island. Accordingly, a decision
was made by the tugs skipper, in conjunction
with the tow master, to proceed west of Little
Green Holm Island on a route which the chart
indicated had a depth in excess of 20 metres.
Again the barge legs were lowered, this time
to 13 metres, to reduce expected rolling as
they crossed the tidal flow to the north of the
Falls of Warness. At 1755 hrs on 8 September
2006 the rigs two forward legs grounded
heavily in a position 3 cables south, south
west of Little Green Holm Island. The nearest
sounding indicated on the chart showed a
depth of 26 metres. The OCTOPUS was refloated
40 minutes later and subsequent
survey showed that all 4 legs were found to
be damaged. Repair costs were in the region
of USD2 million.
Following the grounding the area was
immediately surveyed using modern methods
which revealed a depth of 7.1 metres; as
would be expected this amendment was the
subject of a Notice to Mariners. A more general
and significant lesson to be learnt is that many
areas of the world have not been surveyed by
modern methods, if at all. Changing patterns
of usage - for example, the Shetland Isles is
becoming increasingly utilised by cruise
vessels and, as in this case, tidal/wave energy
developers - means that navigators have to
take particular note of the age and
methodology of surveys upon which their
charts are based. Had the passage planners for
the OCTOPUS rig taken note of the source
data shown on the chart, they would have
perhaps been surprised to learn that the area
was last surveyed by HMS MASTIFF in 1844
and that the methodology used was lead-line
depth sounding. Further the BA chart carried
the warning: depths in these areas have not
been systematically surveyed. Depths in these
areas are from miscellaneous lines of passage
sounding on old lead-line surveys. Un-charted
dangers may exist.
Mariners of course could and should also refer
to the Admiralty Sailing Directions or pilot
books to give warning of unreliable depths.
Although those involved with the passage
planning of the OCTOPUS could have been
more aware of these factors, there was a
significant amount of bad luck involved in the
incident. The area had in fact been surveyed
in early 2006 by a modern commercial survey
vessel and changes to the charted depth
were noted. Unfortunately the significant 7.1m
shoal patch was not noted because the
southern limit of the surveyed area stopped
less than 200 metres north of the unknown
7.1 metre shoal. The full MAIB report is
available on:
www.maib.gov.uk/cms_resources/Harold_Octopus.pdf
Although of little use navigationally,
navigators may be interested to note that
there is a summary report on the status of
hydrographic surveys worldwide available at:
www.iho.shom.fr./PUBLICATIONS/S-55/S_55.htm
The table of geographic areas in the latter site
gives a percentage of those areas which
require re-survey on a larger scale or with
modern techniques and those areas which
have never been systematically surveyed.
There are some surprising results. For example,
35% of USA waters are deemed to require
re-survey at larger scales or to modern
standards. The figure for Japan is 53%. The
Orkney and Shetland Islands remain 65% unsurveyed.
Only 1% of Vietnamese waters is
deemed to have been adequately surveyed.
MISCELLANEOUS
Bunker delivery by tank truck in Nigeria - to be avoided
One of our Members suffered difficulties
when required by charterers to take delivery
of diesel by tank truck at Apapa in Nigeria. As
soon as tank trucks began delivery from the
jetty it became clear that the hoses used were
in poor, if not unsafe, condition. Continual
leakage occurred on the jetty throughout the
delivery of what was supposed to be 240
M/Ts. Despite continual protest by the ship
neither the charterers nor the bunker
suppliers made any attempt to either clean up
the spill or indeed stop the leakage. It was
clear that to avoid delay and penalty from the
local authorities the ship would have to
undertake the clean up of the jetty despite
neither causing the spill nor being able to
prevent it. To add insult to injury the bunker
suppliers threatened to detain the vessel
should the vessel not agree that 250 M/Ts of
diesel was delivered, whereas ships figures
indicated that only 223.46 M/Ts were
delivered. Correspondents (African Marine Services) advised that circumstances in
Nigeria are such that the suppliers extortion
would probably be supported by the courts
or the Port Authorities should the supplier
wish the vessel be detained. Correspondents
advise that there is little that can be done to
ameliorate such circumstances except to
avoid bunkering alongside by tank truck
and to persuade charterers not to do so.
USCG Alert on pneumatic
pump maintenance
The US Coast Guard (USCG) has issued
Marine Safety Alert 4-07
(http://www.uscg.mil/hq/g-m/moa/docs/
4-07.pdf ) concerning a recent incident in
which the crew experienced difficulty
manually deploying the vessels life rafts
from their mounting cradles.
The life rafts were fitted with individual
Hammar Manual Remote Release System
(MRRS) pneumatic vacuum pump units.
When the pumps are manually operated a
vacuum is quickly and easily created that
actuates a corresponding Hammar H20
hydrostatic release unit. In this case a large
number of the pumps failed to activate the
hydrostatic release units as they had not
been lubricated as required. In order to
launch all of the vessels life rafts successfully
the crew had to manually cut the life raft
canister lashings.
The casualty investigation is not complete
and additional recommendations are likely
to follow. However, in the interim, the USCG
strongly recommends that Hammar MRRS
pneumatic pump units, as well as all other
survival equipment, be maintained in
accordance with the manufacturers
recommended maintenance schedules.
Publications
Handy guide to SECAs and SOx
Messrs Shiptalk Legal Guides, in cooperation,
with Clyde & Co law firm have
produced a small booklet giving a simple
outline of SECAs and SOx regulations.
Copies are available from Clyde & Co
(£10 each).
email: Andrew.preston@clydeco.com email: Cris.partiridge@clydeco.com
Editor's message
We are always looking for ways to maintain and increase the usefulness, relevance and general interest of the articles within Risk Watch. Please forward any comments to: rwatched@triley.co.uk
|